Skip Navigation Links
Environmental Assessments
Hospital EIA
Client: AlThika Group

The EIA study for the proposed hospital was conducted according tothe Decree No. 8633/2012 and included the following stages:

  1. Environmental Scoping
  2. EIA Report

The scope of work of the EIA study comprisedthe following main tasks:

  • Assessment of the environmental baseline conditions in the project area;
  • Identifying the potential negative and positive impacts, including socio-economic impacts, that will be induced by the proposed project;
  • Identifying relevant stakeholders and conducting public consultation with these stakeholders;
  • Formulating mitigation measures for the identified negative impacts; and
  • Preparation of an environmental management plan (EMP).